J
Jeff Sweeney
Imagine you have a project that is scheduled from the finish date, but
you have some tasks that are "As soon as possible"
When MS Project reschedules uncompleted work, the "As soon as
possible" tasks that that were scheduled to start but haven't yet have
their constraint changed to "Do not start before". However since the
project is from the finish date, these tasks now appear to behave like
the default, "As late as possible". They now are NOT scheduled to
begin as early as they should. (I still want them to still behave as
soon as possible, just not to start before today's date…not as late as
possible.)
I suppose I could pre-select the tasks that I want, and choose the
"Selected tasks" option but on a large project that isn't very fun.
…and when the updates come from resources through the PWA, things seem
to get even stranger.
Anyone know of a better way?
Thanks!
MS Project Pro 2002 (Server) 10.0.2002.0502
you have some tasks that are "As soon as possible"
When MS Project reschedules uncompleted work, the "As soon as
possible" tasks that that were scheduled to start but haven't yet have
their constraint changed to "Do not start before". However since the
project is from the finish date, these tasks now appear to behave like
the default, "As late as possible". They now are NOT scheduled to
begin as early as they should. (I still want them to still behave as
soon as possible, just not to start before today's date…not as late as
possible.)
I suppose I could pre-select the tasks that I want, and choose the
"Selected tasks" option but on a large project that isn't very fun.
…and when the updates come from resources through the PWA, things seem
to get even stranger.
Anyone know of a better way?
Thanks!
MS Project Pro 2002 (Server) 10.0.2002.0502