I routinely experience a problem where it appears that remaining work does
not get rescheduled when I update a project. i.e. the resource usage view
shows incomplete work in the past.
Am I missing something here? Is there a way to force this incomplete work
forward?
The process I use right now is
1. Reset the status date
2. Tools, Tracking, Update Project, reschedule uncompleted tasks from "this
date"
I am also using a shared resource calendar.