Hi, we are having a few different issues with our projects. Server 2003.
1. Resources assigned to a task with hours, they recorded no actuals and it
is determined that they will not work on the task so the remaining hours were
eliminated. 1 remaining hour is reappearing, even though resource and project
manager reduced rem work to 0 and published.
2. I am seeing on only a handful of tasks and not on all projects, but when
we try to utilize the reschedule work tool, the remaining work is pushed as
expected, but after synching with actuals the remaining work is pushed back
to it's original place in the past.
Just to clarify, the sync with actuals is only looking at actual work and no
other fields in Web Access, so it shouldn't be tied to remaining work?
Any clarification on how to better use these tools will be greatly
appreciated.
DClarcq
1. Resources assigned to a task with hours, they recorded no actuals and it
is determined that they will not work on the task so the remaining hours were
eliminated. 1 remaining hour is reappearing, even though resource and project
manager reduced rem work to 0 and published.
2. I am seeing on only a handful of tasks and not on all projects, but when
we try to utilize the reschedule work tool, the remaining work is pushed as
expected, but after synching with actuals the remaining work is pushed back
to it's original place in the past.
Just to clarify, the sync with actuals is only looking at actual work and no
other fields in Web Access, so it shouldn't be tied to remaining work?
Any clarification on how to better use these tools will be greatly
appreciated.
DClarcq