C
Catalin Pitis
Hi all
I have a Project Server 2003 installed and I'd like to reserve resources for
one project between two specific dates, but without assigning them to tasks
in that project. Is there any possibility to do that in Project Server?
Thanks
Catalin
I have a Project Server 2003 installed and I'd like to reserve resources for
one project between two specific dates, but without assigning them to tasks
in that project. Is there any possibility to do that in Project Server?
Thanks
Catalin