Reserving resources on project with no task assignments

C

Catalin Pitis

Hi all

I have a Project Server 2003 installed and I'd like to reserve resources for
one project between two specific dates, but without assigning them to tasks
in that project. Is there any possibility to do that in Project Server?

Thanks
Catalin
 
C

calihdog

There isn't a way to do that today that I know of. I'd recommend making a
placeholder task and assigning the resources to that until you have the real
tasks to assign them to. Then you could just delete the placeholder.

HTH
 