At one point I opened up the working days to a full 7-day week. Now I need
to reset the working days back to 5-day week. In MS P 2003, I have done the
Tasks --> Define Gen'l project working hours at 8 per day, but some tasks
still show Saturday, Sunday working times. How do I reset the schedule and
remove references to Sat / Sunday work hours?