Reset the < Timesheet > view

R

Reuter

Using MSProject 2003ent

How do I reset the "Timesheet view" in PWA? I copied some new views into my
Production instance.
 
D

Dale Howard [MVP]

Reuter --

As you have discovered, there is no Undo button when you copy a PWA view
from one instance to another. Therefore, the best I can do is to offer you
the list of fields on the View My Tasks page, in the default order in which
they are displayed. They are:

Task Name
Work
% Work Complete
Actual Work
Remaining Work
Start
Finish
Submitted On
Project
Resource Name
Project Manager
Lead Name

Hope this helps.
 