Reset UIDs

Joined
Sep 29, 2016
Messages
1
Reaction score
0
I'm currently working on a project with a 1400 line IMS (Project 2013 file). We are adding another project and want to use the existing Project file as the template for the new project to retain the same look and feel.

I did a "save as" on the old file and saved to another name, then zapped all the tasks. When I start adding tasks for the new project, the UID numbers start where the old project stopped. What can I do to get the new Project file make the first task start with UID "1"?
 