J
JHutchings
In the Gnatt Chart - Entry view the Indicator column displays Workgroup
indicators that reflect the status to requests for progress updates. I have
tasks to which the assigned resource did not respond to but that I know is
complete. As such I have updated the task progress.
Is there a way to reset the Workgroup Indicator that says "There has not yet
been a response to the progress information request yet" so that it does not
display anymore?
indicators that reflect the status to requests for progress updates. I have
tasks to which the assigned resource did not respond to but that I know is
complete. As such I have updated the task progress.
Is there a way to reset the Workgroup Indicator that says "There has not yet
been a response to the progress information request yet" so that it does not
display anymore?