Resolving Conflict for Resources

S

Seraphim

I have several projects merged into one project. From the master project, I
am trying to resolved conflicts for a resource pool that is shared by all of
the projects. When I use the leveling feature to decrease the resources units
spent on a task, it changes the duration to 0 wks. Is there a way to have
the duration of the task keep it's original duration and push the finish time
for that task back because the resource will work on it on another day?
 
J

Jan De Messemaeker

Hi,

You probably didn't use Project's Resource Leveling because it does exactly
what you ask for and not what you describe.
Leveling does not change Work nor Units, it only delays tasks to avoid the
overallocation!
What else did you do?

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top