D
Dale Howard [MVP]
Perl --
This is basically a training and performance issue, since you cannot force
the system to allow only 50% Units for each team leader for the resource in
question. One thing the TL's can do, however, is to change the Max Units
value for the resource in the Resource Sheet view of a project. This change
will be temporary, and will last only while the project is currently open.
This change will allow the TL to assign the resource to tasks without
entering a Units value and then the system will then automatically enter 50%
Units because that is the Max. Units value. Just a thought. Hope this
helps.
This is basically a training and performance issue, since you cannot force
the system to allow only 50% Units for each team leader for the resource in
question. One thing the TL's can do, however, is to change the Max Units
value for the resource in the Resource Sheet view of a project. This change
will be temporary, and will last only while the project is currently open.
This change will allow the TL to assign the resource to tasks without
entering a Units value and then the system will then automatically enter 50%
Units because that is the Max. Units value. Just a thought. Hope this
helps.