L
lynne baker
Hi
Project Pro 2002
Project server 2002
PWA
Please can you tell me how I can add a resource to an existing task
without it showing them as overallocated for the time before they
joined the company.
I have a chap just started, I've allocated him to a task which started
in April and so for that month my resource usage chart shows him as
overallocated.
Is it just a case of deleting the hours manually from the resource
usage view?
Many thanks
lynne
Project Pro 2002
Project server 2002
PWA
Please can you tell me how I can add a resource to an existing task
without it showing them as overallocated for the time before they
joined the company.
I have a chap just started, I've allocated him to a task which started
in April and so for that month my resource usage chart shows him as
overallocated.
Is it just a case of deleting the hours manually from the resource
usage view?
Many thanks
lynne