J
jpuls
Thinking that this could be done in the stock Project Server product,
I posted this question in one of the other Project Server groups. I
understand that it is a matter of customizing things, so this post
here:
Let us say we have a resource manager A, and two project managers, B
and C. We also have a resource, Smith, who is being used in B’s
project in December and in C’s project in January. B’s project changes
so that the task Smith was doing in December gets pushed back a couple
of weeks, so that it is half in December and half in January.
Smith is now over committed in January, and Project Managers B and C
have a conflict, which resource manager A is responsible for
resolving.
Resource manager A wants to get an email automatically whenever a
resource gets committed more than 100% so he can manage it as soon as
possible.
What approach should I use to accomplish this goal in terms of custom
development? It seems to me this would be a fairly common need.
Thanks,
Jim
I posted this question in one of the other Project Server groups. I
understand that it is a matter of customizing things, so this post
here:
Let us say we have a resource manager A, and two project managers, B
and C. We also have a resource, Smith, who is being used in B’s
project in December and in C’s project in January. B’s project changes
so that the task Smith was doing in December gets pushed back a couple
of weeks, so that it is half in December and half in January.
Smith is now over committed in January, and Project Managers B and C
have a conflict, which resource manager A is responsible for
resolving.
Resource manager A wants to get an email automatically whenever a
resource gets committed more than 100% so he can manage it as soon as
possible.
What approach should I use to accomplish this goal in terms of custom
development? It seems to me this would be a fairly common need.
Thanks,
Jim