J
jpuls
I have the feeling that the answer to this should be obvious, or was
covered here before, but I have not found it.
Let us say we have a resource manager A, and two project managers, B
and C. We also have a resource, Smith, who is being used in B’s
project in December and in C’s project in January. B’s project changes
so that the task Smith was doing in December gets pushed back a couple
of weeks, so that it is half in December and half in January.
Smith is now over committed in January, and Project Managers B and C
have a conflict, which resource manager A is responsible for
resolving.
Resource manager A wants to get an email automatically whenever a
resource gets committed more than 100% so he can manage it as soon as
possible. How do I do this?
Thanks,
Jim
covered here before, but I have not found it.
Let us say we have a resource manager A, and two project managers, B
and C. We also have a resource, Smith, who is being used in B’s
project in December and in C’s project in January. B’s project changes
so that the task Smith was doing in December gets pushed back a couple
of weeks, so that it is half in December and half in January.
Smith is now over committed in January, and Project Managers B and C
have a conflict, which resource manager A is responsible for
resolving.
Resource manager A wants to get an email automatically whenever a
resource gets committed more than 100% so he can manage it as soon as
possible. How do I do this?
Thanks,
Jim