Resource allocation at 18,000%

J

jov

Hi everybody,
I'm struggling with creating individual assignment actuals in Project
programaticaly, here's what I'm doing:
I have a task with no information explicitely set, I assign a resource
(which has nothing explicitely set) to that task, I then populate the
TimeScaleValues for that assignment that corresponds to 1 day with an
ActualWork of 6h, I repeat this process several times on any one task
using the same resource or different ones(in which case I create a new
assignment) across different days. However when I'm done it shows the
Assignment Units as 18000%+.

Please can anyone help?
 
J

Jan De Messemaeker

Hi Jov,

There must be an error in your code but without looking at it I don't have a
clue
You can copy it in a note here or in a mail sent to me (address is on my
website)
HTH
 
J

jov

Thanks but I've managed to get around the problem by setting the
assignment units to 1.
 