Hi everybody,
I'm struggling with creating individual assignment actuals in Project
programaticaly, here's what I'm doing:
I have a task with no information explicitely set, I assign a resource
(which has nothing explicitely set) to that task, I then populate the
TimeScaleValues for that assignment that corresponds to 1 day with an
ActualWork of 6h, I repeat this process several times on any one task
using the same resource or different ones(in which case I create a new
assignment) across different days. However when I'm done it shows the
Assignment Units as 18000%+.
Please can anyone help?
I'm struggling with creating individual assignment actuals in Project
programaticaly, here's what I'm doing:
I have a task with no information explicitely set, I assign a resource
(which has nothing explicitely set) to that task, I then populate the
TimeScaleValues for that assignment that corresponds to 1 day with an
ActualWork of 6h, I repeat this process several times on any one task
using the same resource or different ones(in which case I create a new
assignment) across different days. However when I'm done it shows the
Assignment Units as 18000%+.
Please can anyone help?