R
Richard
Hi - I am trying to make use of the resource allocation (max units) to
reflect that I have more than 1 person available, but it does not work as
expected.
I created 1 resource called "Resource 1" and set it's max units to 100%. I
then created 3 tasks as Fixed Unit, Effort Driven tasks and allocated this
resource to each task with 40 hours effort (1 working week) and 100% units.
These are the results that I get.......
With the max units for "Resource 1" set to 100%, the 3 tasks happen one in
each week. This is regardless of leveling day-by-day or week-by-week.
With the max units for "Resource 1" set to 200%, 2 tasks happen week 1 and
the 3rd task happens in week 2, as expected. Again, this is regardless of
leveling day-by-day or week-by-week.
With the max units for "Resource 1" set to 150%, with Day-By-Day leveling
the tasks each happen in weeks 1 to 3 with no overlap (as though only 100% of
the resource is available). However, when Week-by-Week levelling is used,
the tasks do overlap, but too much resource is allocated in each week - there
is an extra 50% of a person too much in each week - ie. days 1 and 2 of the
first week have 100% allocated, and days 3, 4 and 5 of the first week have
200% allocated. In week 2 there is days 1, 2 and 3 with 200% and days 4 and 5
with 100%. MSP is telling me that all this work can happen in 2 weeks, when
infact it will also take the 1st day of week 3 to complete.
Is this a calculation error in MSP when not using whole 100% increments in
the available resource allocation, or is there some interesting explanation
for this?
Appreciate any help and advice available.
Thanks
Richard
reflect that I have more than 1 person available, but it does not work as
expected.
I created 1 resource called "Resource 1" and set it's max units to 100%. I
then created 3 tasks as Fixed Unit, Effort Driven tasks and allocated this
resource to each task with 40 hours effort (1 working week) and 100% units.
These are the results that I get.......
With the max units for "Resource 1" set to 100%, the 3 tasks happen one in
each week. This is regardless of leveling day-by-day or week-by-week.
With the max units for "Resource 1" set to 200%, 2 tasks happen week 1 and
the 3rd task happens in week 2, as expected. Again, this is regardless of
leveling day-by-day or week-by-week.
With the max units for "Resource 1" set to 150%, with Day-By-Day leveling
the tasks each happen in weeks 1 to 3 with no overlap (as though only 100% of
the resource is available). However, when Week-by-Week levelling is used,
the tasks do overlap, but too much resource is allocated in each week - there
is an extra 50% of a person too much in each week - ie. days 1 and 2 of the
first week have 100% allocated, and days 3, 4 and 5 of the first week have
200% allocated. In week 2 there is days 1, 2 and 3 with 200% and days 4 and 5
with 100%. MSP is telling me that all this work can happen in 2 weeks, when
infact it will also take the 1st day of week 3 to complete.
Is this a calculation error in MSP when not using whole 100% increments in
the available resource allocation, or is there some interesting explanation
for this?
Appreciate any help and advice available.
Thanks
Richard