V
verossa
Hi All,
I am new to MS Project and want to ensure when I set up my project it
provides the maximum scheduling / budgeting / reporting flexibility to meet
with the changing demands of the project I have a theoretical question
about the most flexible method to assign resource. I understand the
resource can be assigned as follows:
ID Task Duration Resource
1 Create Post 5 Person 1 [1.0], Person 2 [3.0], Person 3
[1.0]
The same scenario can be represented as main / sub-tasks:
ID Task Duration Resource
1 Create Post 5
1.1 Create Post 1 Person 1[1.0]
1.2 Create Post 3 Person 2[3.0]
1.3 Create Post 1 Person 3[1.0]
Can someone please describe / clarify the pro's & con's of both methods and
what impact (if any) both methods have on scheduling / budgeting /
reporting? When is it best to use one against the other - does it really
matter or is it personal preference?
I'd appreciate any insights from the NG.
Thank in advance - Vers
I am new to MS Project and want to ensure when I set up my project it
provides the maximum scheduling / budgeting / reporting flexibility to meet
with the changing demands of the project I have a theoretical question
about the most flexible method to assign resource. I understand the
resource can be assigned as follows:
ID Task Duration Resource
1 Create Post 5 Person 1 [1.0], Person 2 [3.0], Person 3
[1.0]
The same scenario can be represented as main / sub-tasks:
ID Task Duration Resource
1 Create Post 5
1.1 Create Post 1 Person 1[1.0]
1.2 Create Post 3 Person 2[3.0]
1.3 Create Post 1 Person 3[1.0]
Can someone please describe / clarify the pro's & con's of both methods and
what impact (if any) both methods have on scheduling / budgeting /
reporting? When is it best to use one against the other - does it really
matter or is it personal preference?
I'd appreciate any insights from the NG.
Thank in advance - Vers