Hi All,
I have created a few tasks in a project and assigned resources t
tasks. I have a questions regarding allocation of resources
Scenario:
Task T1 starts on 1st and Ends on 15th
I have two resources R1 and R2. R1 is available only from 1st to 10t
and R2 is available from 7th to 15th to work on this task T1.
How do i allocate the resources based on the dates they are availabl
for this task ? Is it possible to provide a range ?
-Ajee