T
tommcbrny
Hi, I have a two-part question about resources in MS Project:
1) Resources on my project spend ~10% of their time each day on support,
which takes them away from project work. I understand that I can simply
allocate each resource to be available only 90% of the day. I would rather
have this 10% support allocation show up in a graphical resource view such as
the Resource Graph, however. Is this possible (perhaps 10% of the time
shaded in yellow, project allocation time in blue, overallocation in red)?
2) Resources on my project have different skill levels. Work estimated for
a task is estimated on the assumption that a Level 1 resource (highest skill
level) will do the work. If a level 2 resource is assigned, however, it will
take them twice as long. Is it possible to create weighting for resources so
that their work and duration for tasks matches their skill level?
Thank you!
Tom
1) Resources on my project spend ~10% of their time each day on support,
which takes them away from project work. I understand that I can simply
allocate each resource to be available only 90% of the day. I would rather
have this 10% support allocation show up in a graphical resource view such as
the Resource Graph, however. Is this possible (perhaps 10% of the time
shaded in yellow, project allocation time in blue, overallocation in red)?
2) Resources on my project have different skill levels. Work estimated for
a task is estimated on the assumption that a Level 1 resource (highest skill
level) will do the work. If a level 2 resource is assigned, however, it will
take them twice as long. Is it possible to create weighting for resources so
that their work and duration for tasks matches their skill level?
Thank you!
Tom