M
Michelle
I'm trying to level my project from a specific start date
based on work effort. This works fine at the same
category level, but different resources assigned to
independent tasks within a category look as if the second
task is dependent on the first. The 2nd task date does
not start until the first task is complete. There is no
predecessor. How can I get both tasks to start at the
same time, for instance?
Suggestions, please.
Thanks,
Michelle
based on work effort. This works fine at the same
category level, but different resources assigned to
independent tasks within a category look as if the second
task is dependent on the first. The 2nd task date does
not start until the first task is complete. There is no
predecessor. How can I get both tasks to start at the
same time, for instance?
Suggestions, please.
Thanks,
Michelle