Is it best to define resource by role or by individual person? I have a
number of tasks which are essentially project management but are being
carried out by different people, some of them solution architects. These
people have different global cost rates. Or is it possible to assign a
cost to an individual task? I need to be able to track how many project
management or solution architect activity days I've used as these are
defined in the contract and the costs then won't match.
Or am I just thinking too deeply about this ;-)
Many thanks,
R
--
rooster99
------------------------------------------------------------------------
rooster99's Profile:
http://forums.techarena.in/members/150192.htm
View this thread:
http://forums.techarena.in/microsoft-project/1293391.htm
http://forums.techarena.in
I see you have 2 critical requirements - "cost rates of solution
architects can vary" and "you need to know how many solution architect
activity days I've used".
I can provide you three options with its pros and cons
1. Individual resources - Add the resource details in Resource sheet
for each team member
Pros: (1) Working time of each resource can be different (2) Cost
rates of each resource can be different
Cons: (1) Huge list of resource names (2) You can effectively
categorize the resources by skillset (but still can do it by adding
custom fields)
2. Group resources - For each role, define one resource in resource
sheet, but with Max Units reflecting the number of resources with that
role
Pros: (1) Small list of resources
Cons: (1) Working time can be set at role level, and not at individual
resources (2) For each role, the cost rate should be constant
3. Cost resources - You can go with (1) and (2), but don't define the
cost of the resources at resource level. Instead, create a Cost
resource (if you are using Project 2007) or insert a field "Fixed
cost" in Gantt chart to enter the cost
Pros: (1) Simple, if the cost is not dependent on time or number of
resources
Cons: (1) Cost resource and fixed cost is provided to enter cost that
doesn't vary over time
Please let us know if this helps
- Sai, PMP, PMI-SP, MCT, MCTS
http://saipower.wordpress.com