Resource Allocation

D

Devendra Bhagat

I want to allocate one resource to one project in which he should not be
spending more than 2 hours per day.

While assigning the task to the resource I am setting the units to 25%
because we work eight hours. This however does not allocate the resource
across five days if there are five task on which the resource is to work.
Instead what it does is it allocates the user for 2 hours same time on the
same day for all five days. The duration I have specified for this task is 2
hours where as work is only of 2 hours

Any solutions?

Devendra
 
J

Jan De Messemaeker

Hi,

In Resource Sheet, put 25% as Max Units for the resource
Tools, Resource Leveling, Level Now.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top