D
Devendra Bhagat
I want to allocate one resource to one project in which he should not be
spending more than 2 hours per day.
While assigning the task to the resource I am setting the units to 25%
because we work eight hours. This however does not allocate the resource
across five days if there are five task on which the resource is to work.
Instead what it does is it allocates the user for 2 hours same time on the
same day for all five days. The duration I have specified for this task is 2
hours where as work is only of 2 hours
Any solutions?
Devendra
spending more than 2 hours per day.
While assigning the task to the resource I am setting the units to 25%
because we work eight hours. This however does not allocate the resource
across five days if there are five task on which the resource is to work.
Instead what it does is it allocates the user for 2 hours same time on the
same day for all five days. The duration I have specified for this task is 2
hours where as work is only of 2 hours
Any solutions?
Devendra