J
jgv2004
Hello, I have a question relating to resource allocation:
say that I've defined a one-person team for installing a pc and its
supporting peripherals and it takes him/her 'X' number of hours to finish
this task.
Now, if a second and/or third person of comparable skill and effort is
available for the install, is there a way to input "2 x one-person team" or
"3 x one-person team" and get updated results (available resource hours,
task duration, etc.) for a 2-person or a 3-person install schedule by
manipulating the gannt chart or via a macro? Or would I have to define the
work of a 2-person and 3-person team and then change the resource(s)
allocated for the relevant task?
Thanks for any help.
say that I've defined a one-person team for installing a pc and its
supporting peripherals and it takes him/her 'X' number of hours to finish
this task.
Now, if a second and/or third person of comparable skill and effort is
available for the install, is there a way to input "2 x one-person team" or
"3 x one-person team" and get updated results (available resource hours,
task duration, etc.) for a 2-person or a 3-person install schedule by
manipulating the gannt chart or via a macro? Or would I have to define the
work of a 2-person and 3-person team and then change the resource(s)
allocated for the relevant task?
Thanks for any help.