C
CDR
I have several tasks all available to start at the same time, all requiring
the same resource. They are summary tasks, with sub tasks below. Once I
start subtask1, I want to continue using the resource until I have finished
the last subtask for the summary.
If I assign the resource at the summary level, I am told that the resource
is overallocated, and that the overallocation cannot be resolved. I can skip
the allocation of that resource, or just stop leveling. Why won't the
resource be allocated to one of the tasks, and then allocated to the other
task when the first task is complete?
the same resource. They are summary tasks, with sub tasks below. Once I
start subtask1, I want to continue using the resource until I have finished
the last subtask for the summary.
If I assign the resource at the summary level, I am told that the resource
is overallocated, and that the overallocation cannot be resolved. I can skip
the allocation of that resource, or just stop leveling. Why won't the
resource be allocated to one of the tasks, and then allocated to the other
task when the first task is complete?