J
JR Winder
Can't seem to figure how to make this simple thing happen.
I have two tasks: Task A, Task B. Task A has a five day duration and a
single resource assiged to it at 50% (20 hrs of allocated work during the
five day duration)
Task B has a duration of 2 hours and a signle resource assigned to it at
100%. The resource for Task B is the same as Task A.
When Project scheduleds these two tasks it schedules each to begin on
separate weeks. The resource usage for Task A is 50% for five days. Since
Task B only takes two hours I assumed Project would fit tje two hours for
Task B to begin and end on one of the days Task A is scheduled for since the
resource is only at 50% for Task A work.
Without setting too many constraints on either Task what do I need to change
in order for Project to recognize the available time for other tasks (Task
B) duirng the same time Task A is being worked on?
Thanks in advance for any help on this.
JR
I have two tasks: Task A, Task B. Task A has a five day duration and a
single resource assiged to it at 50% (20 hrs of allocated work during the
five day duration)
Task B has a duration of 2 hours and a signle resource assigned to it at
100%. The resource for Task B is the same as Task A.
When Project scheduleds these two tasks it schedules each to begin on
separate weeks. The resource usage for Task A is 50% for five days. Since
Task B only takes two hours I assumed Project would fit tje two hours for
Task B to begin and end on one of the days Task A is scheduled for since the
resource is only at 50% for Task A work.
Without setting too many constraints on either Task what do I need to change
in order for Project to recognize the available time for other tasks (Task
B) duirng the same time Task A is being worked on?
Thanks in advance for any help on this.
JR