Mike_In_Sacto
Here is my issue:
We are running Project Professional & Server 2002. The Project Managers are
setting up their schedules in the server and using the Enterprise Resource
Pool to build their project teams. After building their teams, they go into
the Resource Sheet and set the individual allocations (Max Units column) to
the percentages that they have each individual for....Joe - 50%, Mary - 25%,
etc...
After they save their projects to the server and re-open them, the
allocations all go back to 100%.
What are we doing wrong ? (Right now we are having them change the %
allocation at the task level so that they can keep working).
Thanks
We are running Project Professional & Server 2002. The Project Managers are
setting up their schedules in the server and using the Enterprise Resource
Pool to build their project teams. After building their teams, they go into
the Resource Sheet and set the individual allocations (Max Units column) to
the percentages that they have each individual for....Joe - 50%, Mary - 25%,
etc...
After they save their projects to the server and re-open them, the
allocations all go back to 100%.
What are we doing wrong ? (Right now we are having them change the %
allocation at the task level so that they can keep working).
Thanks