J
jaime
Hi,
I'm working with MS Project 2003 and I have the following question.
I have about 50 tasks and they're assigned as follow:
Task1 Takes 20 effort hours.
Task1 is assigned to 2 people - Jim and Peter.
Jim and Peter are assigned to work 70% of their 40 hour week = .7*40 = 28
hours.
Task1 also assigns Peter to work 12 hours and Jim 8.
However, after assigning all the hours I get Peter and Jim's names in RED.
I did the following to the resources.
In the Resource sheet I set "Max Units" for both Peter and Jim at 70%
Then I went and assigned their names to the tasks. Then went to Resource
Usage and applied the number of hours each resource can work on the task.
I still see both names in Red and with a yellow flag. How do I view this
and how can I fix it? Thank you for your help.
I'm working with MS Project 2003 and I have the following question.
I have about 50 tasks and they're assigned as follow:
Task1 Takes 20 effort hours.
Task1 is assigned to 2 people - Jim and Peter.
Jim and Peter are assigned to work 70% of their 40 hour week = .7*40 = 28
hours.
Task1 also assigns Peter to work 12 hours and Jim 8.
However, after assigning all the hours I get Peter and Jim's names in RED.
I did the following to the resources.
In the Resource sheet I set "Max Units" for both Peter and Jim at 70%
Then I went and assigned their names to the tasks. Then went to Resource
Usage and applied the number of hours each resource can work on the task.
I still see both names in Red and with a yellow flag. How do I view this
and how can I fix it? Thank you for your help.