Resource and Standard Calendar

T

TKeire

Hi

I am using Project 2003. I have a project with multiple resources. I have
a standard calendar and then individual resource calendars to reflect any
variances from the standard calendar for the different resources.
My standard calendar shows Sunday and Monday 25/26 June as Non working days.
For resource "A" I have changed these dates to "working". For resource "A"
if I schedule a task to start on the 22/06 with 11d dur it works fine and
allows work through the 25/06 and 26/06. It does not appear to work for the
following scenario:

Task 1, Resource "A" starts on 22/06/06
Task 2 is scheduled "SS & 11d lag" to Task 1, also Resource "A".
For some reason it is jumping the 25/06 and 26/06 even though these are
programmed as working days for Resource "A", thus my 11d lag is really a 13d
lag.

I have played around with this for quiet awhile and can't seem to find any
sensible soln, apart from changing the lag to 9d which is really tricking the
computer. Of course this also leads to the scenario that this problem may be
occurring in other areas that I have not noticed yet!

Ideas/suggestions please?

Tony
 
R

Rod Gill

Task lag is calculated based on the Standard calendar. Lag has nothing to do
with resource calendars, so edits to a resource calendar has no effect.

You can create a New calendar with 25/26 as working and edit the successor
task to use the new calendar. To do this double-click the successor task,
click the Advanced tab and select your new base calendar in the Calendar
field.

Project uses the Task's calendar (default Standard Calendar) to calculate
when the Lag finishes.
 
T

TKeire

Thanks Rod, that sorted that one

Rod Gill said:
Task lag is calculated based on the Standard calendar. Lag has nothing to do
with resource calendars, so edits to a resource calendar has no effect.

You can create a New calendar with 25/26 as working and edit the successor
task to use the new calendar. To do this double-click the successor task,
click the Advanced tab and select your new base calendar in the Calendar
field.

Project uses the Task's calendar (default Standard Calendar) to calculate
when the Lag finishes.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top