K
KGMSP
Resource Assignment Dates not the same as task level dates.
For Example:
Task: Build Radio - 40 days dur. 1/30/06 to 3/24/06
Resources: John 100hrs & Bill 60hrs.
I want both John and Bill's hours spread evenly across the duration, however
my schedule now in the task usage view shows only John (resource with most
hrs) spread across the duration and Bill's hours are at a much shorter date.
I want them both spread evenly across the entire duration. All of my tasks
are fixed work and they need to stay that way. I can manually go into task
usage and fixed the dates, however once status is taken Project reverts back
to the above.
Is their a setting in project I am missing?
Is it because of fixed work?
Please help!!!!
Thanks,
KG
For Example:
Task: Build Radio - 40 days dur. 1/30/06 to 3/24/06
Resources: John 100hrs & Bill 60hrs.
I want both John and Bill's hours spread evenly across the duration, however
my schedule now in the task usage view shows only John (resource with most
hrs) spread across the duration and Bill's hours are at a much shorter date.
I want them both spread evenly across the entire duration. All of my tasks
are fixed work and they need to stay that way. I can manually go into task
usage and fixed the dates, however once status is taken Project reverts back
to the above.
Is their a setting in project I am missing?
Is it because of fixed work?
Please help!!!!
Thanks,
KG