B
Babar.Asif
Suppose 2 resources were assigned to a task. However, only one resource
worked on it. Now how should you enter the actual hours given that I
don't want to unassign the resource from the task and republish it?
Should I enter actual work = 0hr and remaining work = 0hr for that
resource who didn't work on the task? When I do that, the task doesn't
show as complete in the resource timesheet.
Any suggestions would be helpful.
Babar
worked on it. Now how should you enter the actual hours given that I
don't want to unassign the resource from the task and republish it?
Should I enter actual work = 0hr and remaining work = 0hr for that
resource who didn't work on the task? When I do that, the task doesn't
show as complete in the resource timesheet.
Any suggestions would be helpful.
Babar