Resource assignment on project server shows wrong results

  • Thread starter Deshwal - Magus India
  • Start date
D

Deshwal - Magus India

Hi,

I plan a project, assign resources, level resources ... public project on
project server ...

The resource assignment on project server shows overallocation for few
resources on some days .. although on the project professional side the
resource sheets shows perfectly leveled resources ... can someone help..
 
D

Dale Howard [MVP]

Deshwal --

You need to tell us what version of Project Server you are using. 2002,
2003, or 2007? Assuming you are using 2007, you need to actually publish
the schedule changes after leveling using File - Publish. Hope this helps.
 
D

Deshwal - Magus India

Dale Hi ... Thanx for responding to my question ... I am using project server
2007 .. and i did publish the changes after leveling the resources ..
suprisingly this is happening for few resources only ....


Dale Howard said:
Deshwal --

You need to tell us what version of Project Server you are using. 2002,
2003, or 2007? Assuming you are using 2007, you need to actually publish
the schedule changes after leveling using File - Publish. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top