resource Assignment view not showing baseline

N

Novica B

When trying to view resource assignments via the PWA. The baseline values are
not showing. why is this? I have confirmed that the project is baselined and
when I look at the schedule via Project Centre the baseline is there, but
when viewing via resource centre, no baseline values, please help.

Thanks
Novica B
 
D

Dale Howard [MVP]

Novica B --

You must include the baseline fields as Published Fields for each project in
the Project Server database before the baseline values will display in the
View Resource Assignments page. To do so, complete these steps:

1. Open a project
2. Click Tools - Customize - Published Fields
3. Add the appropriate baseline fields to the list on the right
4. Click the OK button
5. Click Collaborate - Publish - Republish Assignments and then click OK
6. Repeat steps #1-5 for each project

You should probably also add the baseline fields to the Published Fields
list in each of your enterprise project templates as well. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top