N
Novica B
When trying to view resource assignments via the PWA. The baseline values are
not showing. why is this? I have confirmed that the project is baselined and
when I look at the schedule via Project Centre the baseline is there, but
when viewing via resource centre, no baseline values, please help.
Thanks
Novica B
not showing. why is this? I have confirmed that the project is baselined and
when I look at the schedule via Project Centre the baseline is there, but
when viewing via resource centre, no baseline values, please help.
Thanks
Novica B