P
peter.weinstein
Hello;
I am a software developer and I use Microsoft Project 2003 to estimate the
duration of a task given the work that is required and the availability of
resources. At the start of a project I determine the tasks that need to be
performed, the work that is required and the availability of resources (if
possible).
I have configured Project so that my tasks are Fixed Work. In the past I
have first input the amount of work that is required to perform the task and
second assigned a resource to the task. What I recently discovered is that
Project will adjust the availability of a resource when I follow this
sequence. This is an unwanted result and yields an estimated duration that
is greater than expected. However, if I change the sequence so that I first
assign a resource to a task and second input the amount of work that is
required, Project will accept the availability that I have assigned for the
resource and will estimate the duration correctly.
It is more natural for me to first input the work and second assign the
resource. Is it possible to configure Project so that I can proceed in this
manner while preventing any change to resource availability once the resource
is assigned? I believe that this would then yield an accurate estimated
duration. This would be beneficial because sometimes the resource is not
known (or their availability) when the work is initially input.
If I have to change the sequence, can you explain why Project requires that
I first assign the resource and second input the work? Also, if I later have
to adjust the availability of a resource or swap resources will Project
continue to provide an accurate estimated duration?
Thank you for your help.
I am a software developer and I use Microsoft Project 2003 to estimate the
duration of a task given the work that is required and the availability of
resources. At the start of a project I determine the tasks that need to be
performed, the work that is required and the availability of resources (if
possible).
I have configured Project so that my tasks are Fixed Work. In the past I
have first input the amount of work that is required to perform the task and
second assigned a resource to the task. What I recently discovered is that
Project will adjust the availability of a resource when I follow this
sequence. This is an unwanted result and yields an estimated duration that
is greater than expected. However, if I change the sequence so that I first
assign a resource to a task and second input the amount of work that is
required, Project will accept the availability that I have assigned for the
resource and will estimate the duration correctly.
It is more natural for me to first input the work and second assign the
resource. Is it possible to configure Project so that I can proceed in this
manner while preventing any change to resource availability once the resource
is assigned? I believe that this would then yield an accurate estimated
duration. This would be beneficial because sometimes the resource is not
known (or their availability) when the work is initially input.
If I have to change the sequence, can you explain why Project requires that
I first assign the resource and second input the work? Also, if I later have
to adjust the availability of a resource or swap resources will Project
continue to provide an accurate estimated duration?
Thank you for your help.