Hi All,
How do I track resource assignemnt for a task?Suppose if a resource is
assigned 20 may, 21 may etc. Where will i find these assignments?
thanks & regards,
BBN
 
J

Jan De Messemaeker

Hi,

In the Task Usage View, by task, and in the resource Usage view, presented
by resource.
HTH
 
J

Jan De Messemaeker

Hi,

Just came uop that since this is in the developer NG, you might mean in VBA.
Look for help on
TimescaleValue, TimescaleValues
Timescaledata

Objects.
HTH
 