K
karishma
i want to add resources not by particular name, but with the group name. e.g.
project leader, project engineers and design engineers.
in my project most of the subtasks are going to be done by design engineers.
if i assign design engineers to them, project indicates overallocation of
resource. even assignment units against these tasks are 100% in task sheet
view. is it possible to name resources under the grooup name of design
engineers?
also is it possible to enter assignment units against the resoource name,
not against the assigned task?
e.g. resource name work assignment units
design engineers 570 hrs 300%
task 1 150hrs
120%
task 2 200 hrs
80%
task 3 220 hrs
100%
is it possible?
thanks
project leader, project engineers and design engineers.
in my project most of the subtasks are going to be done by design engineers.
if i assign design engineers to them, project indicates overallocation of
resource. even assignment units against these tasks are 100% in task sheet
view. is it possible to name resources under the grooup name of design
engineers?
also is it possible to enter assignment units against the resoource name,
not against the assigned task?
e.g. resource name work assignment units
design engineers 570 hrs 300%
task 1 150hrs
120%
task 2 200 hrs
80%
task 3 220 hrs
100%
is it possible?
thanks