We have a situation where on certain tasks, when we view
a resources asssignments they are not showing up. This
only seems to occur when a Team Member creates a new
task, which then gets approved by the Project Manager,
and then the TM books time agains the Task. In the View
Resource Assignments view the assignments against this
task do not appear. Does anyone have any ideas as to what
steps we may be missing out?
thanks
Alex
We have a situation where on certain tasks, when we view
a resources asssignments they are not showing up. This
only seems to occur when a Team Member creates a new
task, which then gets approved by the Project Manager,
and then the TM books time agains the Task. In the View
Resource Assignments view the assignments against this
task do not appear. Does anyone have any ideas as to what
steps we may be missing out?