T
TraceyH
I have 2 issues-
1) I show a 'red' overallocation condition after auto-leveling when the
assignment is only 3hrs/day. The resource's working time is 4hrs/day and my
project calendar is 4hrs/day. The resource has an 'extra' hour of available
time that is not being scheduled. Why is this happeneing?
2) Even after defining priorites for tasks, the auto-leveling function
insists on pushing some tasks beyond other tasks with lesser priority. This
problem seems to be worse for tasks where I have actual values (actual work
or % complete). I have not baselined the project,and these tasks are not
linked to others or constrained in any way.
1) I show a 'red' overallocation condition after auto-leveling when the
assignment is only 3hrs/day. The resource's working time is 4hrs/day and my
project calendar is 4hrs/day. The resource has an 'extra' hour of available
time that is not being scheduled. Why is this happeneing?
2) Even after defining priorites for tasks, the auto-leveling function
insists on pushing some tasks beyond other tasks with lesser priority. This
problem seems to be worse for tasks where I have actual values (actual work
or % complete). I have not baselined the project,and these tasks are not
linked to others or constrained in any way.