Resource availability date range issue

J

jstowell

Every resource in Resource Center under 'View Availability' shows a date
range of 4/10/08 -> 4/24/08 and nothing else. I checked the Enterprise
Resource Pool, General page, Resource Availability section, and the
'Available To' entry is set to 'NA'. The standard calendar looks OK. Can
anyone suggest another place to look?
Thanks,
jstowell
 
M

Marc Soester [MVP]

HI jstowell,

I am sure you have done this, but will ask anyway :) have you changed the
from and to date within the View Availabillity screen so that you can see a
differnt date range?

If not I go to Settings > View Options and within the option page change the
date range.
Hope this helps
 
J

jstowell

Marc,
No I hadn't done that. I knew it had to be something simple; I just didn't
know where else to look. Now, thanks to you I do!
Thanks so much for taking the time to respond!
jstowell
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top