Resource availability drops to zero for my resources...

R

richardsantink

Hi folks,

I have a bizarre problem going on... All of my resources when displayed in
the Resource center, show 0 availability as of July 31st, 2007. They also
show no availability before a certain date, also. Frequently the message
"Warning: Availability data has not been published for one or more resources
in the selected date range." appears in the Resource Center view, although
refreshing seems to eliminate it.

Does anyone know why my resources seem to have no availability? I checked
my calendars, and they all appear normal.

Running PS2003, SP2a

Thanks,

Rich
 
D

Dale Howard [MVP]

Rich --

You might try this:

1. Open the Enterprise Resource Pool for editing and check out one of the
troublesome resources (no availability after the 30th)
2. Double-click the name of the resource.
3. Examine the Resource Availability grid at the bottom of the General
page.

The Resource Availablility grid show contain a single line with information
as follows:

NA NA 100%

If it doesn't show that, then change it to reflect the correct availability.
Any changes you make will show up the next time the OLAP cube rebuilds. If
this solves the problem, then do the same for every problematic resource.
Let us know if this helps.
 
R

richardsantink

Dale,

Thanks! At first I thought that it did not work, but when I checked again
about 20 minutes later, all is well. :)

Rich
 