Resource Availability Graph in Project Server 2007

J

JP

I'm seeing a discrepency in the Resource availability graph and what a
published Gantt chart is showing. Basically, the resource availability graph
is no longer showing the resource as having work on a particular date, when
the gantt chart clearly shows the assignment. Also, from the Resource
center, when I click View Assignments for that resource, the assignment is
shown just as it is in the Gantt chart.

The weird thing is, the Resource Availability graph once showed this
resource as having work for that project. Since then the Gantt was edited
and published, but the particular assingment I'm seeing problems with was not
changed. So, I'm seeing the assignment for this resource in the Gantt chart
and on the Resource assignments view from the resource center - but not
seeing this assignment on the Resource availability graph.

Any thoughts?

Thank you in advance,
JP
 
B

Ben Howard

Hi Robbie, I would always check directly between MS Project and the Resource
availability graph. Open the plan from the working store (not the cache),
change something on that assignment, and republish - make sure the task is
published (eg task publish field = Yes (this is the default) and the the
booking type is committed). If there is still a discrepency then you have a
bug....
 
J

JP

Thanks Ben. It looks like there's a bug.... This is a very disturbing bug,
as I use this graph to help decide when we can take on new work.
 