We cannot get the resource availability to work on PWA. The projects
are all published and the work shows up on the bar chart under resource
availability. However in the hours spreadsheet below the bar chart it
contains all zero hours for "work" and "availability". The OLAP cube
builds but it sys it has errors that will not prevent use of the cube.
Any thoughts????

Thanks in advance.....

Rob
 
D

Dale Howard [MVP]

Rob --

The errors with the building of the OLAP cube are the source of your
resource availability problems as resource availability is calculated when
the OLAP cube builds.
 