G
Gil
Hi all,
We are using Project Server 2007, and I am trying to establish a
process to support the following scenario in one of our departments:
2 Project managers, each manages 4 small projects.
4 developers, all work together on all projects (mostly bug fixing or
small developments).
For every project there are some prioritized tasks waiting to be
worked on.
At the beginning of the week the project managers post a weekly plan
for each of the resources (for example: On Monday, res1 will work on
proj3, res2 on proj5, res3 on proj7 etc. on Tuesday res1 continue
working on proj3, res2 on proj1 etc).
How to describe this kind of resource availability in the plan? how to
level resources? Any best practices for a scenario like this?
I will appreciate any thoughts.
Thanks, Gil
We are using Project Server 2007, and I am trying to establish a
process to support the following scenario in one of our departments:
2 Project managers, each manages 4 small projects.
4 developers, all work together on all projects (mostly bug fixing or
small developments).
For every project there are some prioritized tasks waiting to be
worked on.
At the beginning of the week the project managers post a weekly plan
for each of the resources (for example: On Monday, res1 will work on
proj3, res2 on proj5, res3 on proj7 etc. on Tuesday res1 continue
working on proj3, res2 on proj1 etc).
How to describe this kind of resource availability in the plan? how to
level resources? Any best practices for a scenario like this?
I will appreciate any thoughts.
Thanks, Gil