K
Kelly Becker
We are running Project 2007 with Project Server - SP2. The problem we are seeing is with Resource Usage in the enterprise - in the thick client. We have resources who are shared on multiple projects. When a PM was using the thick client and was looking at the availability of their resources in the Resource Usage view, this shared resources had assigned hours in the "other projects" area of the view, but there were no hours associated with any of the projects listed. So..the "other projects" total was 5 hours, but each project under that heading had nothing. When I went to PWA to the Resource Center, the resource had 0h on that day. But I wanted to know what was causing this problem, so I began systematically opening each project under "other projects". Sure enough, the second project I opened had 5 hours for this resource. When I republished that plan (PM says they had published already), the 5 hours showed up appropriately everywhere. Any idea what could have caused this? If the publish had an error, wouldn't the 5 hours just not show up anywhere? Why did it show up in only the "other projects" total column and not with the project that had the hours? Any help would be appreciated as we need to understand how to mitigate this issue.
Thanks!
Kelly
Submitted via EggHeadCafe - Software Developer Portal of Choice
Get Started with SQLite and Visual Studio
http://www.eggheadcafe.com/tutorial...b-b6f46d4f2c6a/get-started-with-sqlite-a.aspx
Thanks!
Kelly
Submitted via EggHeadCafe - Software Developer Portal of Choice
Get Started with SQLite and Visual Studio
http://www.eggheadcafe.com/tutorial...b-b6f46d4f2c6a/get-started-with-sqlite-a.aspx