I'm hoping that someone has an easy answer for me. In Project 2007,
I'm trying to show how many people from a Generic trade group
(electricians for example) are available on each day of the week. For
instance, I want to show that on every Monday, there are 5
Electricians working, 18 in on Tue - Thur and 13 in on Fridays. I can
specify a date range in the Resource availability table but that only
specifies one Monday. I want to know if there's a way to select every
Monday rather than only one particular Monday. Any help would be
greatly appreciated.
Thanks, Doug.
 
B

Ben

The only way to do this, assuming all the underlying data is correct is via
Analysis Services. In there you can select multiple individual days.
 