Resource Availability Never Changes in Portfolio Analyzer

C

Charles Simpson

Anyone know why the "availability" field under "Totals" in Portfolio Analyzer
never changes? All of our resources seem to have the exact same availability
(1,875 hours/year) even if they are scheduled for work or have reported
actuals. Seems like this should reduce their availability.

Example:

Resource Work Actual Work Availability
Charles Simpson 125.5h 68.25h 1,875h
Mike Lambert 1,225.1h 768.5h 1,875h

Any ideas?

We are running Project Server 2003 with SP1

Charles L. Simpson
 
E

Ellen Lehnert, PMP

The availability you are looking at is a reflection of the availabilty based
on their calendar. It is not doing a calculation of work - availability. If
you would like that number, add a calculated field to the OLAP view.
 