K
Keith Loewen
I have a fixed work task of 80 hours. Assigned one person at 100% so the
duration is 2 weeks. Assigned a second person at 100% so duration moves to 1
week. Perfect. Used Resource Availability to set up a second person with 0%
availability for the first week and 100% availability for the second week.
Inserted a second 80 hour fixed work task that starts after the second person
has 100% availability. Assigned both resources, duration is 1 week.
Perfect. HOWEVER, if I assign the second person to the first task so that
availability starts in the middle of the 2 week task duration, MS Project
assigns at 0% for the entire 2 week task. I expected that the person would
be assigned at 0% for the first week and 100% for the second week when they
become available at 100%, thereby reducing the duration from 2 weeks to 1.5
weeks. What am I missing?
duration is 2 weeks. Assigned a second person at 100% so duration moves to 1
week. Perfect. Used Resource Availability to set up a second person with 0%
availability for the first week and 100% availability for the second week.
Inserted a second 80 hour fixed work task that starts after the second person
has 100% availability. Assigned both resources, duration is 1 week.
Perfect. HOWEVER, if I assign the second person to the first task so that
availability starts in the middle of the 2 week task duration, MS Project
assigns at 0% for the entire 2 week task. I expected that the person would
be assigned at 0% for the first week and 100% for the second week when they
become available at 100%, thereby reducing the duration from 2 weeks to 1.5
weeks. What am I missing?