Ricardo
Hello
We are using MS Project Server 2007, SP1 with MS SQL-server 2005. We
have renamed a project and did changes in the project afterwards
(moving tasks in time, changing resources, update remaining work
etc.). When I view the availability of one resource of the project,
then I see the project twice in the details grid: once with the old
name and once with the new name. The data of the project with the new
name is correct, but the data of the project with the old name seems
to be the data from a while ago. Now the resource shows a over
allocation for a project that does not exist in the system.
When I do a look at the list of enterprise objects which is shown when
you want to delete a project, then there is only the object with the
new name available.
I've seen this behaviour for more then one project.
Does anyone know what we do wrong? Is it a bug? Is there a workaround
for it?
Ricardo
We are using MS Project Server 2007, SP1 with MS SQL-server 2005. We
have renamed a project and did changes in the project afterwards
(moving tasks in time, changing resources, update remaining work
etc.). When I view the availability of one resource of the project,
then I see the project twice in the details grid: once with the old
name and once with the new name. The data of the project with the new
name is correct, but the data of the project with the old name seems
to be the data from a while ago. Now the resource shows a over
allocation for a project that does not exist in the system.
When I do a look at the list of enterprise objects which is shown when
you want to delete a project, then there is only the object with the
new name available.
I've seen this behaviour for more then one project.
Does anyone know what we do wrong? Is it a bug? Is there a workaround
for it?
Ricardo