hi,
in summary: how do i schedule a resource to be available from a certain date
on a per project basis (rather than a global basis)?
detailed description:
i want a particular resource to start work on a project (project 1) on a
certain date - lets say July 1st 2008.
This resource is currently scheduled to do some work on another project
(project 2) up until that time, however I am scheduling some 'free time'
between projects to allow for loose ends to be tidied up. I dont want to
create a dependency between the projects.
I use Resource Levelling on both projects.
Currently, project 1 is inside project server, and project 2 is not (and
therefore does not use the shared resource enterprise pool).
The only way that I have found to makle all of my resources tasks schedule
in project 1 from 1st July on project 1 is to change his global resource
calander to say resource available from.
HOWEVER, obviously if i add project 2 into project server then this will
block that plan from working how i intend.
surely there must be a way to phase resource on and off a project without
playing with the global caleneder?
any help or tips would be great thanks,
pete
in summary: how do i schedule a resource to be available from a certain date
on a per project basis (rather than a global basis)?
detailed description:
i want a particular resource to start work on a project (project 1) on a
certain date - lets say July 1st 2008.
This resource is currently scheduled to do some work on another project
(project 2) up until that time, however I am scheduling some 'free time'
between projects to allow for loose ends to be tidied up. I dont want to
create a dependency between the projects.
I use Resource Levelling on both projects.
Currently, project 1 is inside project server, and project 2 is not (and
therefore does not use the shared resource enterprise pool).
The only way that I have found to makle all of my resources tasks schedule
in project 1 from 1st July on project 1 is to change his global resource
calander to say resource available from.
HOWEVER, obviously if i add project 2 into project server then this will
block that plan from working how i intend.
surely there must be a way to phase resource on and off a project without
playing with the global caleneder?
any help or tips would be great thanks,
pete