Are there any known issues with the Resource Availability Report in the
PS2007 Resource Center?
Here is the issue we are having...
Scenario: 1 resource, 1 task assignment for the month of January @ 100%
utilization. Assignment of 147 hours for the month for this task. He is not
assigned as a resource on any other project or any other task for this month.
The 'Resource Availability' Report in Project Web Access -- Resource Center
is showing the following for the month of January 2009.
Availability: -85.5
Capacity: 140
Data Warehouse Project: 225.5
Then in other months he should be over allocated and the report in PWA is
showing that he has no allocation for those months.
For the month of January we were execting to see ---> Capacity: 147
Availabity: 78.5 Instead it is showing it as an over allocation and it is
under by 7 hours.
We have spent hours looking @ this and not understanding how the program is
getting these calculations.
PS2007 Resource Center?
Here is the issue we are having...
Scenario: 1 resource, 1 task assignment for the month of January @ 100%
utilization. Assignment of 147 hours for the month for this task. He is not
assigned as a resource on any other project or any other task for this month.
The 'Resource Availability' Report in Project Web Access -- Resource Center
is showing the following for the month of January 2009.
Availability: -85.5
Capacity: 140
Data Warehouse Project: 225.5
Then in other months he should be over allocated and the report in PWA is
showing that he has no allocation for those months.
For the month of January we were execting to see ---> Capacity: 147
Availabity: 78.5 Instead it is showing it as an over allocation and it is
under by 7 hours.
We have spent hours looking @ this and not understanding how the program is
getting these calculations.