Resource Availability Table

M

MJP_CCH

I am using the Resource Availablity table to set a productivity rating per
month on each resource in my schedule. I have some tasks that span over 2
months that have different productivity ratings. Why doesnt project pick up
the different productivity ratings?
 
J

Jan De Messemaeker

Hi,

Resource Availability does only what it promises - it sets availability.
Which % of time a resoruce is to spend on a task (assignment units) is
decided by you and you alone.
The availability % will only help to tell whether or not the resoruce is
overallocated - and play a part in Resource Leveling.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 