Resource Availability View Customization

B

Bubba

In the Resource Availability, there is a view called "Assigned Work by
Project" that breaks down the work of each resource by project. I need to
modify this view (or create a new view) to be able to filter the projects
shown based on a custom field "Project State". This will allow me to see a
certain resource's work based on projects that are "Urgent", "Pending", etc...

In Manage Views, the Resource Availability views are not available for edit.
Also, I can't find a way to include a Project custom field when creating a
Resource Center view.
 
D

Dale Howard [MVP]

Bubba --

Alas, the Project Server administrator cannot create custom Resource
Availability views or modify the four default views. Sorry.
 
M

Marc Soester [MVP]

Hi Bubba,

You can create your own views within the Data Analyser. You can essentially
achieve the same view with the option to filter by Project.
Hope this helps
 