B
Bubba
In the Resource Availability, there is a view called "Assigned Work by
Project" that breaks down the work of each resource by project. I need to
modify this view (or create a new view) to be able to filter the projects
shown based on a custom field "Project State". This will allow me to see a
certain resource's work based on projects that are "Urgent", "Pending", etc...
In Manage Views, the Resource Availability views are not available for edit.
Also, I can't find a way to include a Project custom field when creating a
Resource Center view.